6) Presentation of final design (fully inked and coloured) this can usually take place within 4-6 weeks of the survey and site assessment dependant upon the complexity of the site.
7) Production of detailed planting plans following approval of the final design, and if required, detailed planting plans can be drawn up. This part of the process should take no more than 4 weeks from approval of the final design. If you wish, we can also produce a plant schedule for each area of the garden which can be sent to appropriate nurseries to organise the sourcing of the plants.
8) Carrying out of tender process to contractors if required, we can produce a specification document detailing the proposed works which we will send to a number of landscape contractors in order to receive their quotes. It may be necessary to include construction drawings and a setting out plan with the specification document.
|